2022-04-222015-2019 crash analysisCompleted

City of Santa Monica Local Roadway Safety Plan prepared by Nelson\Nygaard Consulting Associates. The plan analyzes 2015-2019 crash data, establishes a severity-weighted Priority Network, and identifies safety emphasis areas and candidate interventions. CCR retains it as background to the later 14th Street project, whose 2026 contract record has separately documented Culver City institutional and professional connections.

Local Roadway Safety PlanDocumented

Record Details

Consultant

Nelson\Nygaard Consulting Associates, Inc.

Crash Data Period

2015-2019

Total Crashes

2334

Fatal Crashes

15

Severe Injury Crashes

110

Fatal And Severe Total

125

Priority Network Method

Half-mile segments ranked by severity-weighted crash value; segments added until 50 percent of the citywide weighted crash value was represented.

Priority Network Centerline Share

14 percent

Related Vision Zero Intersection

Olympic Boulevard and 14th Street

Ccr Relevance

Background only; Culver City bridge is established by later 2025-2026 person, vendor, court, and regional-governance records.

Organizations

Projects

Events

Relationships

Categories

Themes

Record Notes

The LRSP reports 2,334 local-street crashes for 2015-2019. Its Priority Network is built from half-mile street segments ranked by severity-weighted crash value until the selected segments account for 50 percent of the citywide weighted value; the resulting network represents 14 percent of centerline miles and more than 50 percent of severity-weighted crashes. A review of Figure 11 does not show 14th Street as a continuous Priority Network corridor. The report explicitly lists California Avenue and 14th Street among top unsignalized after-dark crash locations, with three total crashes, two after dark, and one fatal/severe after-dark crash. Separate City Vision Zero material identifies Olympic Boulevard and 14th Street as a high-priority intersection with a history of vehicle, bicycle and pedestrian collisions. Do not collapse these intersection-specific findings into a claim that the entire 14th Street corridor was designated as a 2022 LRSP Priority Network corridor without additional source support. CCR relevance is intentionally narrow: the LRSP provides background to the later 14th Street project. The later 2026 contract has documented Culver City bridges through Kimley-Horn's Culver City municipal/project work and Ellis Raskin's separate MOVE Culver City appellate and Westside COG roles. Neither Kimley-Horn nor Raskin is presented here as an author or decision-maker for the 2022 LRSP.