Jubilo Village / YMCA — Parking, Construction Mitigation and Developer-Described Funding Gap

December 2025-March 2026 Documented correspondence; cost figures are developer statements
At a glance

City and Community Corporation emails document Jubilo Village and YMCA negotiations over construction mitigation, shared driveway access, possible compensation and parking. In March 2026, Community Corporation Executive Director Tara Barauskas described YMCA-related issues as creating an additional $1.7 million-$4 million funding gap. She later wrote that the burden included $1.7 million for resident parking and another $2.4 million for construction-term parking, and separately described a $1.7 million closing holdback as money Community Corporation had not been repaid because of resident-parking loss.

Project-development / parking / construction relationship Direct City and developer emails
What the record shows

Key facts

Address
4460-4464 Sepulveda Boulevard, Culver City, California
Financial context
Developer-described project costs / holdback tied to parking and construction conditions
Documented amounts
$1.7M-$4M · $1.7M · $2.4M
Evidence

Primary source

Navigate the archive

Linked records

Direct links named in this record: people, organizations, properties, projects, events and other canonical archive records.

More context

Related records

Ranked by documented overlap such as a shared project, property, person, organization, event, relationship, or an explicit link between records.

Archive indexing

Record tags

Use these archive labels to follow related people, organizations, subjects and records across Culver City Records.

Context note

The dollar figures are statements by Community Corporation personnel in the email production. CCR does not independently characterize them as City obligations, verified losses, or approved reimbursements.